KEY PROJECT 05
REDEVELOPMENT OF LAFARGE RAWANG PLANT
Demolition of 100-Meter Height Chimney & Other Plant's Steel Structures
THE FASTEST & SAFEST CHIMNEY
DEMOLITION IN MALAYSIA
'Flying Elephant' Demolition Machines
Challenges
• Adjacent to live operational process facilities & lives services.
• Existing chimney structure have cracks with rebar exposed (no manual hacking works allowed).
• Demolished using custom made demolition machine operated using remote control lifted by mobile crane.
Safe demolition adjacent to live services.
Safe Demolition Adjacent to Live Services
Our experience includes high reach demolition & selectively dismantling plant's structures adjacent to live operational process facilities & live services.
Detailed planning & coordination with our client allows us to ensure that we complete each project with minimal effect to our clients business activities.