top of page

KEY PROJECT 04

KLCC EAST UNDERGROUND STATION (KVMRT LINE 2) 

Demolition Works of Multi-storey Carpark (Superstructure & Substructure) 

Demolition MRT Malaysia

DAY

10

Demolition Contractor Malaysia

DAY

45

Demolition Project in Malaysia

DAY

30

Demolition work in MRT Project Malaysia

DAY

75

11 WEEKS ONLY  TO FULLY DEMOLISH

High Rech Demolition KLCC
Malaysia Demolition KLCC

Challenges

• Precast structure buildings with hollow core slab.

• Require extra attention to structure stability during demolition.

• Surrounded by high end high-rise & low-rise residential building.

• Near to KLCC Twin Tower tourist attraction area.

bottom of page